Investments made by Enea Operator in 2018:

  • Construction of GPZ [1] Choszczno II;
  • Construction of GPZ [1] Recz;
  • Reconstruction of GPZ [1] Zdroje;
  • Reconstruction of GPZ [1] Dąbie;
  • Reconstruction of GPZ [1] Żary;
  • Construction of overhead 110 kV overhead line Choszczno II - Recz.

Investments planned for the next years by Enea Operator:

  • Construction of a 110 kV overhead line from Pniewy to Nowy Tomyśl;
  • Construction of a 110 kV overhead line from Środa to Kromolice;
  • Construction of the RS Garaszewo with the reconstruction of 110 kV overhead line between Kromolice - Nagradowice, Kromolice - Swarzedz (section from the SE [2] Kromolice to GPZ [1] Nagradowice) and the construction of a new 110 kV line from Kromolice to Gadki (section from the SE [2] Kromolice to GPZ [1]); Nagradowice
  • Construction of a 110 kV overhead line from Babimost to Zbąszynek;
  • Construction of a new 110 kV switchgear in GPZ [1] Fordon with the construction of a double-circuit 110 kV overhead cable from Fordon - cut line 110 kV from Jasiniec to Świecie;
  • Construction of a 110 kV cable line from Bydgoszcz Północ to Bydgoszcz Śródmieście;
  • Construction of the 110 kV overhead line from Piła Krzewina to Miasteczko Krajeńskie;
  • Reconstruction of 110 kV linear sequence from Morzyczyn to Drawski Młyn;
  • Construction of leads from SE [2] Baczyna;
  • Modernization of the 110 kV line of the Leśniów - Bytnica - Debrznica - Sulęcin route;
  • Reconstruction of linear line 110 kV from Gorzów (Baczyna) - Witnica - stand 65 to Dębno;
  • Reconstruction of the 110 kV overhead line from Wronki to Czarnków Płty;
  • Reconstruction of the 110 kV overhead line from Gryfino to Żydowce;
  • Reconstruction of the 110 kV overhead line Recław - Nowogard - Maszewo;
  • Construction of GPZ [1] Skwierzyna II with a power line;
  • Construction of GPZ [1] Garbary with 110 kV cable connections;
  • Construction of GPZ [1] Towarowa;
  • Construction of GPZ [1] Suchy Las;
  • Reconstruction of GPZ [1] Pomorzany;
  • Reconstruction of GPZ [1] Leszno Gronowo;
  • Reconstruction of GPZ [1] Wronki;
  • Reconstruction of GPZ [1] Piła Południe.

Investments made by Enea Wytwarzanie in 2018:

  • Installation of the Catalytic Flue Gas Denitrification System (SCR [3]) on the 500 MW unit No. 10;
  • Adjustment of the production equipment to conclusions (BAT [4]);
  • Modernization of the 200 MW unit electrostatic precipitator No. 6.

Investments planned for the subsequent years by Enea Wytwarzanie:

  • Installation of the Catalytic Flue Gas Denitrification System (SCR [3]) on the 500 MW unit No. 9;
  • Replacement of an electro filter of the 500 MW block No. 9;
  • Adjustment of the manufacturing equipment to conclusions BAT [4];
  • Modernization of the 200 MW unit electrostatic precipitator No. 2;
  • Modernization of the 200 MW unit electrostatic precipitator No. 7.

Investments made by Enea Elektrownia Połaniec in 2018:

  • Installation of the Catalytic Flue Gas Denitrification System (SCR [3]) on unit No. 4.

Source URL: https://raport2018.csr.enea.pl/en/explore-our-investments

[1] https://raport2018.csr.enea.pl/en/lexicon/5/letter_g#GPZ
[2] https://raport2018.csr.enea.pl/en/lexicon/5/letter_s#SE
[3] https://raport2018.csr.enea.pl/en/lexicon/5/letter_s#SCR
[4] https://raport2018.csr.enea.pl/en/lexicon/5/letter_b#BAT